BHEL wins contract to setup 500MW unit at Bokaro TPS

24 June 2008 - Indian power engineering major Bharat Heavy Electricals has won a INR18.4bn ($428m) turnkey contract from the Damodar Valley Corporation for setting up a 500MW generating unit at the Bokaro thermal power station in the state of Jharkhand, India.

Three units of 210 MW each, built by Bharat Heavy Electricals (BHEL), are already in operation at Damodar Valley Corporation's (DVC) Bokaro thermal power station (TPS).

BHEL's scope of work includes design, engineering, manufacture, supply, erection and commissioning of steam turbines, generators, boilers, associated auxiliaries, balance of plant and electricals, besides controls and instrumentation, electrostatic precipitators and civil works.




| Add RSS Feed


 
Return to Previous Page

 
Power Engineering Webcasts




LIVE AT COAL-GEN:
The Real Meaning of 'Carbon Capture Ready'

Original broadcast on
August 14, 2008






LIVE AT COAL-GEN:
Heat Rate Improvement Through Intelligent SootBlowing

Original broadcast on
August 13, 2008






Air Pollution Control and Ash Handling Systems Solutions
Original broadcast on
December 12, 2007



More

Sponsored White Papers Library
Recently Added White Papers

How Automation Technology Can Improve Performance of Your Power Plant (08/25/2008, Honeywell)

Security Solutions to Meet NERC-CIP Requirements (08/24/2008, Honeywell)

More
Featured White Papers

Evaluating cogeneration for your facility: A look at the potential energy efficiency, economic and environmental benefits (06/02/2008)

More

 







 


Subscribe eNewsletter Magazines