Duke Energy receives coal plant air permit

29 January 2008 -- The North Carolina Department of Environment and Natural Resources' (DENR) Division of Air Quality issued a final air permit for an 800 MW advanced clean-coal unit planned at Duke Energy's Cliffside Steam Station.

Cliffside's final air permit includes emissions limits for SO2 and NO that are stricter than federal or state requirements. It also includes a commitment from Duke Energy Carolinas to address the emission of CO2.

Once the new unit comes online in 2012, Duke Energy will retire four older generating units capable of generating approximately 200 MW at the Cliffside site.

Construction of the new unit is expected to begin immediately.



Related Articles of Interest:

Duke receives air permit for coal gasification power plant

Kentucky advanced-coal project obtains air permit

Episode 2: Ten Steps to Achieving Success with Your Air Quality Permit (podcast)


Power Engineering Click Here to Subscribe to the Power Engineering E-Newsletter




| Add RSS Feed


 
Return to Previous Page

 
Power Engineering Webcasts




Squeeze More Out of Your Power Plant by Modernizing Your Control System
Original broadcast on
November 20, 2008






Turbine Inlet Cooling with Indirect Evaporation - With Greater Density Comes More Power
Original broadcast on
October 29, 2008






LIVE AT COAL-GEN:
The Real Meaning of 'Carbon Capture Ready'

Original broadcast on
August 14, 2008



More

Sponsored White Papers Library
Recently Added White Papers

How Automation Technology Can Improve Performance of Your Power Plant (08/25/2008, Honeywell)

Security Solutions to Meet NERC-CIP Requirements (08/24/2008, Honeywell)

More
Featured White Papers

Evaluating cogeneration for your facility: A look at the potential energy efficiency, economic and environmental benefits (06/02/2008)

More

 







 


Subscribe eNewsletter Magazines