E.ON reserve position on CNE conditions

28 July 2006 - Spain's Comisión Nacional de Energía (CNE) decided on Thursday to approved E.ON's bid for Endesa subject to a number of conditions.

The CNE notified E.ON that agreement was conditional on E.ON divesting about 7600 MW of Endesa's generating capacity in Spain. E.ON said that it had not yet received the decision in writing but planned to review the conditions in detail. E.ON said it saw no justification for the conditions it is already aware of and reserves all legal options.

In a statement E.ON said it is strongly committed to the acquisition and believes that it will benefit all stakeholders: customers, employees and shareholders as well as the wider Spanish economy.

Following its detailed review of the CNE decision, E.ON will inform the market of any further action it may take.




| Add RSS Feed


 
Return to Previous Page

 
Power Engineering Webcasts




Squeeze More Out of Your Power Plant by Modernizing Your Control System
Original broadcast on
November 20, 2008






Turbine Inlet Cooling with Indirect Evaporation - With Greater Density Comes More Power
Original broadcast on
October 29, 2008






LIVE AT COAL-GEN:
The Real Meaning of 'Carbon Capture Ready'

Original broadcast on
August 14, 2008



More

Sponsored White Papers Library
Recently Added White Papers

Evaluating cogeneration for your facility: A look at the potential energy efficiency, economic and environmental benefits (06/02/2008, Cummins Power Generation)

More
Featured White Papers

Evaluating cogeneration for your facility: A look at the potential energy efficiency, economic and environmental benefits (06/02/2008)

More

 







 


Subscribe eNewsletter Magazines